J. Ray McDermott, S.A. set a benchmark in the industry for fabrication, completion and delivery of a 15,500-metric ton float-over deck in 22.5 months. Delivery to the Cuu Long Joint Operating Company (CLJOC) of Vietnam allowed production to begin ahead of schedule from the Su Tu Vang (Golden Lion) oil field.

Comprised of a jacket, float-over topsides, pipelines, umbilicals, PLEMS and living quarters for 66 people, the Su Tu Vang Central Processing Platform (CPP) is a fully integrated EPCI project. This project boasts development of an eight-pile almost cuboid jacket and optimization of a construction-friendly float-over deck with unique design challenges that were overcome by the expense of the joint J. Ray-CLJOC project team. The CPP is designed to process 100,000 bopd. The output from the field is expected to be approximately 65,000 bpd. The remaining capacity of Su Tu Vang CPP will be used to process production from the Su Tu Den (Black Lion) North East oil field, scheduled to commence in 2010.

[ILLUSTRATION OMITTED]

Upon the contract award in March 2006, the first steel cutting ceremony for the deck took place on Sept. 28, 2006 and within just 22.5...

To continue reading

FREE SIGN UP